Completion date: February 17, 2026
Location: Toledo, OH
The gymnasium's hardwood flooring was significantly affected, requiring extensive removal, remediation, air quality control, and debris hauling to restore the area.
Our team initiated the project by setting up containment barriers at the gymnasium exits. We deployed an advanced air filtration system, including 5 large 1400 cfm Air Filtration Devices (AFDs) and 7 smaller 550 cfm units, to ensure air quality. All affected hardwood flooring was meticulously removed, followed by thorough HEPA vacuuming of all areas of concern. A plant-based antimicrobial agent was applied to prevent future growth. Finally, two large truckloads of debris were hauled back to our shop for proper disposal.